Basics of Building Construction Process Step by Step

building construction process

Every person needs a building to reside. Apart from residential purposes, buildings are required for industrial purposes, educational and business purposes, and the storage of materials.

Understanding the basics of building construction helps in building a building project successfully.

In this article, the steps involved in building construction are explained in detail.

Basic Steps in Starting a Building Construction Project

The building construction process basically involves two major stages:

  1. Pre-Construction Phase
  2. Construction Phase

Pre-Construction Phase

The pre-construction phase in a building construction project consists of the following stages:

  1. Acquire Land
  2. Choose a Technical Consultant and a Design Professional
  3. Prepare the Building Plan
  4. Prepare Estimate
  5. Interview Contractors
  6. Get your Permits

Construction Phase

The construction phase in a building construction project consists of the following stages:

  1. Site clearance
  2. Site Surveying and Layout
  3. Excavation
  4. Foundation
  5. Plinth
  6. Walls & Column
  7. Sills, lintel & chhajja
  8. Doors and windows
  9. Floors
  10. Roofs
  11. Steps, stairs & lifts
  12. Finishing work
  13. Building services.

1. Pre-Construction Phase of a Building Construction Project

  1. Acquire Land:

    This is the most important step in building construction. The most important factor to consider before purchasing land is its location. Based on your exact needs, you want to assess the location of the lot and its proximity to facilities such as public transport, highways, schools, parks, etc. If you already have land, half of your problem ends here.

  2. Choose a Technical Consultant and a Design Professional

    The technical consultant will help you create a plan and detailed scope of work for your building project, which is generally done by an Architect and Structural Engineers.

  3. Prepare Estimate

    The building estimator estimates the amount of material, the number of different items of work and produces a sheet containing the total cost of the building project.

  4. Interview Contractors

    The selection of a good contractor is crucial to the successful construction of the building project within the time frame and to maintain the quality of construction at the same time.

  5. Get Your Permits

    This is an important task once the project is ready for execution. For that, you have to get permission from the local municipal body before starting construction.

Also Read: Difference between Shuttering, Formwork, Scaffolding & Centering

2. Construction Phase in a Building Project

    1. Site Clearance :

      Site preparation is the first activity of the construction phase of the building project. This task involves removing unwanted obstructions from the site such as woods, debris, tree roots, old buildings if present, and leveling the ground area.

    2. Site Surveying and Layout :

      After the completion of site clearance activities, the next phase is the site survey and layout. Site layout survey is the process of interpreting construction plans and marking the location of proposed structures with the help of surveying equipment such as level, theodolite, total station, etc.

    3. Excavation :

      After establishing the layout of the structure, the excavation process starts using suitable machines based on the type of soil and the size of the excavation work.

    4. Foundation :

      Building activity begins with digging the ground for the foundation and then building it. The foundation is the lowest part of the building responsible for transferring the load from the structure to the ground. Therefore, it requires great care and precision during construction.

    5. Plinth :

      The part of the wall between the ground floor and the ground level is called a plinth. It is usually of stone masonry. If the foundation is on the pile, a plinth beam is inserted to support the wall above the floor level. A damp proof course is provided at the top of the plinth. It is usually a 75 mm thick plain concrete course.

    6. Walls & Column :

      The function of walls and columns is to transfer the load of the structure vertically downward so that it can be transferred to the foundation.
      In addition, the wall encloses the building and provides privacy, protection from thieves and insects, and keeps the building warm in winter and cool in summer.

    7. Sills :

      Window frames should not be placed directly above the masonry. It is placed in a 50 mm to 75 mm thick plain concrete course provided above the masonry. This course is called Sill.

    8. Lintels :

      Lintels are reinforced cement concrete or stone beams provided over the door and window openings to support the masonry work over it.

    9. Chhajja :

      Chhajja is an overhanging projection given outside the wall to protect doors and windows from rain.

    10. Doors and windows :

      The job of the door is to give access to different rooms in a building and also to deny access whenever necessary. The building has windows to receive light and ventilation.

    11. Floors :

      The floor is an important component of a building. It gives working/useful areas for the occupants.

    12. Roof :

      The roof is the topmost part of the building which provides the top cover to the building. It should be leakproof.

    13. Stairs & lifts :

      The stairs provide access from floor to floor. Elevators or Lifts are to be provided in all public buildings for the convenience of elderly and disabled persons.

    14. Finishing Works :

      Finishing operations such as ceiling plastering, external and internal plastering of walls begin after the construction of the structure. They are then provided with whitewash, distemper or paint, or tiles.

    15. Building services :

      Water supply, sanitation and drainage work, power supply work, and the construction of cupboards and showcases form the major building services.

Last Words

I hope you got complete information about the Basic Steps in Starting a Building Construction Project in this article.

If you found this article helpful, feel free to share it with your friends.

Leave a comment if I missed anything.

Happy Learning!!